Fill Dirt & Topsoil Calculator

Dirt shrinks when it is compacted, so you need more loose yards than the hole holds. Enter the area and finished depth to get the loose yards to order, weight and truckloads.

Prices for your area

Fill Dirt & Topsoil Calculator — ConcreteNear.com

Tons to order 5.33 tons · $161.02
Tons to order5.33 tons
Cubic yards (loose)4.44 yd³
Area covered200 ft²
Truckloads1
0.5 ft³ bags (small jobs)240

Cost estimate U.S. average prices

Common fill dirt, delivered
4.44 yd³ × $36.23
$161.02
Estimated total$161.02
  • Compact fill in 6–8 in lifts; deep fill under slabs or footings should be tested for compaction.
Email results
Inputs
MaterialCommon fill dirt (~1.2 t/yd³)
Length20 ft
Width10 ft
Depth6 in
Density override (0 = typical for the material)0 tons/yd³
Compaction / settling allowance20%
Truck payload14 tons

Planning estimate only — confirm with your supplier or contractor.

Prices used — edit any price to match your local quote
ItemUnit priceBasis & source
Fill dirt, furnished (borrow, truck measure)
per yd³
public source Florida DOT Item Average Unit Cost 2025, item 0120 2 2 Borrow Excavation, Truck Measure (66 contracts) (2025 lettings) — Furnished and delivered on public jobs; small residential orders and screened topsoil cost more.

Email these results

We send one email with these results to the address you enter — nothing else. We don't store your address or add it to any list.

Get a real quote

Calculators get you close. A local company can quote your exact job.

How to use this calculator

  1. Pick fill, select fill, topsoil or clay.
  2. Enter the area and finished depth.
  3. Use 15–25% shrink for fill that will be compacted.
  4. Read loose yards and loads.

Formulas

  • Loose yd³ = area × depth (in) ÷ 12 ÷ 27 × (1 + shrink %)
  • Tons = yd³ × density (~1.1–1.4 t/yd³)

Questions

How much fill dirt do I need?

A 20 × 10 ft area filled 6 in deep is 3.7 yd³ compacted; with a 20% shrink allowance, order about 4.4 yd³ loose.

How much does a yard of dirt weigh?

About 1.1–1.4 tons depending on soil type and moisture.

Fill dirt or topsoil?

Use fill to raise grade and topsoil only for the top 4–6 in where things will grow.

Sources & assumptions

Prices checked 2026-11-10. State pricing multiplies national figures by the U.S. Bureau of Economic Analysis regional price parities (goods for materials, services for labor and services). RPPs compare general consumer price levels (U.S. = 100). They are not construction-specific; we use RPP Goods for materials and RPP Services: Other (excludes rents) for labor and services.

Results are planning estimates, not quotes or engineering advice. Codes, specifications and your supplier's numbers govern.