Concrete Pump Time & Cost Calculator

Estimate how long the pump will be on site — and what it will bill — by checking the pump's placing rate against how fast the ready-mix trucks can deliver.

Prices for your area

Concrete Pump Time & Cost Calculator — ConcreteNear.com

Billable pump hours 4 hr · $1,060
Billable pump hours4 hr
Pumping time1.67 hr
Concrete supply rate (per hour)24 yd³
Effective placing rate (per hour)24 yd³
BottleneckReady-mix supply
Trucks needed to keep the pump busy7

Cost estimate U.S. average prices

Boom pump time
4 hr × $225.00
$900.00
Per-yard pumping charge
40 yd³ × $4.00
$160.00
Estimated total$1,060
  • The trucks can only deliver about 24 yd³/hr. Ask the plant for 7 trucks to keep up with the pump.
Email results
Inputs
Concrete to pump40 yd³
Pump typeBoom pump
Pump placing rate (per hour)50 yd³
Ready-mix truck size10 yd³
Trucks in rotation3
Truck round trip (plant → site → plant)75 min
Setup + washout time1 hr
Travel time billed (portal to portal)1 hr
Pump minimum hours4 hr

Planning estimate only — confirm with your supplier or contractor.

Prices used — edit any price to match your local quote
ItemUnit priceBasis & source
Boom pump hourly rate
per hr
starting estimate Starting estimate for a mid-size (about 32–42 m) boom. Bigger booms cost more.
Pumping charge per yard
per yd³
starting estimate Starting estimate; many pumpers add a per-yard charge on top of hourly time.

Email these results

We send one email with these results to the address you enter — nothing else. We don't store your address or add it to any list.

Get a real quote

Calculators get you close. A local company can quote your exact job.

How to use this calculator

  1. Enter the yards to pump and the pump type.
  2. Enter a realistic placing rate — crews, not pumps, often set the pace.
  3. Enter truck size, trucks in rotation and their round trip.
  4. Read billable hours and the bottleneck.

Formulas

  • Supply rate (yd³/hr) = trucks × truck size × 60 ÷ round-trip minutes
  • Effective rate = lower of pump rate and supply rate
  • Billable hours = max(minimum, pour hours + setup/washout + travel), rounded up to ½ hr

Questions

How long does it take to pump 10 yards of concrete?

Placing often runs 20–60 yd³ per hour depending on the pump and crew, so 10 yards may take under an hour of pumping — but with setup, washout and minimums, expect to pay for 3–4 hours.

Boom pump or line pump?

Line pumps suit small residential pours and tight access; boom pumps place faster and reach over obstacles.

Why does truck spacing matter?

If trucks can't keep up, the pump waits — and you pay for every hour. The calculator tells you how many trucks keep the pump busy.

Sources & assumptions

Prices checked 2026-11-10. State pricing multiplies national figures by the U.S. Bureau of Economic Analysis regional price parities (goods for materials, services for labor and services). RPPs compare general consumer price levels (U.S. = 100). They are not construction-specific; we use RPP Goods for materials and RPP Services: Other (excludes rents) for labor and services.

Starting estimates No public price series was found for: Boom pump hourly rate; Pumping charge per yard; Line (trailer) pump hourly rate. These defaults are editable placeholders — replace them with a local quote.

Results are planning estimates, not quotes or engineering advice. Codes, specifications and your supplier's numbers govern.